Funding         
Ohio Public Works Commission     $811,000   0%interest loan
ARC Ohio Dept of Development      300,000    Grant
Village contribution                        
    61,000
Total Project                               $1,172,000

Project to increase the plant capacity from 1.2 million gallons per day to 1.8 mgd.
Project to include a new 37' x 40' metal building to house our previously purchased larger sludge
press, new station pumps, polymer system, conveyor, sludge pump, air compressor, waste sludge
pump stations, piping & electrical work.
Two 45' diameter clarifiers.
Relining existing wet well.
Construction began May 5, 2008
Startup of new equipment Jan. 20, 2009
1/8/08        JWC Environmental                         Headworks screen, grinder, conveyor        $106,200.00
1/8/08        Service Pump & Supply     Washwater pump, control panel, A/comp, pump        $27,167.00
1/8/08        Siemens Water Tech                 Polymer feed system                                           $9,938.00
1/8/08        Walker Process Equip                 Clarifier equipment                                         $128,470.00
1/8/08        Serpentix Conveyor Corp                 Conveyor belt equip                                    $39,965.00
3/4/08        Kenney, Inc                             General Contractor                                             $393,654.00
3/4/08        Dixon Electrical Systems         Electrical Contractor                                            $115,000.00
3/4/08        ITT Flygt Cincinnati                  Sewage Pumps                                                    $65,518.93
3/4/08        Fee Corp.                                 Relining Wet Well                                                $47,408.00
3/4/08        American Buildings                 Metal sludge press bldg                                        $47,280.00
4/1/08        McDaniel's Construction         Pipe/fittings   (MBE)                                               $49,942.00
Construction & Material Bids Awarded